TK Concrete of Pella recently began work on the 2019 Parking Lot Reconstruction Project. This project includes the removal of the existing parking lot pavement, construction of new 6” thick Portland cement concrete pavement, new sidewalks, storm sewer, and reconstruction of adjacent alleys and curb along N 2nd Ave W and W 3rd St S.
During the initial excavation work, the crew ran into unforeseen conditions, including some buried brick and rubble from a previous structure on the site, and a couple of utility conflicts.
Even with the recent rains and the unforeseen site conditions encountered, the project is still expected to be finished by the specified completion date of November 29, 2019.